UTC Case Docket Details

Docket Number 230172

Case Docket Details Table
Docket Number UE-230172
Advice 23-01
Company PacifiCorp
DBA Pacific Power & Light Company
Filing Type Tariff Revision
Industry (Code) Electric (140)
Status Closed
Lead Staff Hawkins-Jones, Jacque (UTC)
Filed Date 04/10/2023
Effective Date 05/10/2023
Summary General Rate Case to request an increase in revenues of approximately $26.8 million from Washington operations for the first rate year, effective March 1, 2024. For the second rate year, the requested increase is approximately $27.9 million. (Do Not Change Summary.)

Event History

  • 03/12/2026 -- Allowed (Commissioner Rendahl moved to issue an order, in Docket No. UE-230172, PacifiCorp’s d/b/a Pacific Power & Light Company, filing on July 15, 2025, as revised on January 29, 2026, reflecting its Schedule 94, Capital Review Adjustment, granting the filing, subject to the following conditions: 1. Requiring PacifiCorp d/b/a Pacific Power & Light Company to modify WN U-76, Schedule 94, Capital Review Adjustment, to reflect a reduction in provisional rate base additions of approximately $12.5 million for the period of January 1, 2024, to January 31, 2024. 2. Requiring the company to file tariff revisions to provide customers the $1.3 million refund associated with discrete projects to be effective by April 1, 2026. 3. Requiring the company to provide Commission Staff with all requested documentation concerning reimbursement funds received related to Inflation Reduction Act/Infrastructure Investment and Jobs Act (IRA/IIJA) and the specific projects to which those funds apply, within 30 days. 4. Clarifying that the annual review will not be finalized until Commission Staff is able to verify the outstanding issues concerning federal reimbursement funds, at which time, any additional overcollection will be refunded. 5. Outlining that once Staff has completed its review of requested documentation it will either file a letter of compliance if no additional refund is necessary or set the matter for a future open meeting. Commissioner Doumit seconded the motion. The motion carried (3:0) )
  • 03/13/2026 -- Closed
  • 03/12/2026 -- Open Meeting
  • 05/24/2023 -- Consolidate - Parent
  • 05/05/2023 -- Formal
  • 03/15/2023 -- Pending
  • 03/15/2023 -- Open