UTC Case Docket Details
Docket Number 960326
| Docket Number | UT-960326 |
|---|---|
| Advice | |
| Company |
Qwest Corporation
TCG Seattle |
| DBA | |
| Filing Type | Interconnection Agreement |
| Industry (Code) | Telecommunications (170) |
| Status | Closed |
| Lead Staff | Tom Wilson |
| Filed Date | 02/08/1996 |
| Effective Date | 08/27/2003 |
| Summary | Request for approval of Ninth Amendment to Interconnection Agreement between TCG Seattle and Qwest Corporation, f/k/a U S WEST Communications, Inc. |
Event History
- 08/27/2003 -- Open Meeting (Ninth Amendment)
- 07/23/2003 -- Open Meeting (Eighth Amendment)
- 07/23/2003 -- Effective Date
- 09/11/2002 -- Open Meeting (Seventh Amendment)
- 04/20/2002 -- End of Pending - Reconsideration
- 04/10/2002 -- Open Meeting (Sixth Amendment.)
- 04/10/2002 -- End of Reconsideration
- 04/10/2002 -- Effective Date
- 03/23/2002 -- End of Pending - Reconsideration
- 03/13/2002 -- End of Reconsideration
- 11/29/2001 -- End of Pending - Reconsideration
- 09/01/2001 -- End of Pending - Reconsideration
- 12/23/2000 -- End of Pending - Reconsideration
- 09/21/1998 -- End of Pending - Reconsideration
- 02/17/1997 -- End of Pending - Reconsideration
- 01/15/1997 -- Due date (Due date for Commission approval or rejection of agreement.)
- 11/18/1996 -- End of Pending - Reconsideration
- 11/08/1996 -- Due date (Deadline for Commission resolution of petition for arbitration.)
- 07/17/1996 -- Due date (Last date to file petition for arbitration.)
- 06/24/1996 -- Due date (First date to file petition for arbitration.)
- 02/08/1996 -- Due date (Request for negotiation by TCG to U S WEST.)
- 08/27/2003 -- Approved (Allowed to become effective per Consent Agenda.)
- 07/28/2003 -- Re-open
- 07/23/2003 -- Approved (Approved to become effective per the Consent Agenda.)
- 06/25/2003 -- Re-open
- 09/11/2002 -- Approved (Approved per the Consent Agenda.)
- 08/19/2002 -- Re-open
- 04/10/2002 -- Approved (Approved per Consent Agenda.)
- 03/19/2002 -- Re-open (Request for approval of (sixth) amendment to interconnection agreement on behalf of Qwest from Elizabeth Weber. (Posted))
- 03/13/2002 -- Approved (Approved per Consent Agenda.)
- 02/15/2002 -- Re-open (Request for approval of Four and Fifth Amendments to interconnection agreement on behalf of Qwest from Elizabeth Weber.)
- 11/16/2001 -- Approved (Approved per Consent Agenda.)
- 10/24/2001 -- Re-open (Request for approval of (Third) Amendment to interconnection agreement on behalf of Qwest from Elizabeth Weber.)
- 08/22/2001 -- Approved (Approved per Consent Agenda.)
- 07/27/2001 -- Re-open (Request for approval of (Second) Amendment to interconnection agreement on behalf of Qwest from Adam Sherr.)
- 12/13/2000 -- Approved (Approved per Consent Agenda.)
- 11/16/2000 -- Re-open (Request for Approval of Amendment No. 1, to the Interconneciton Agreement between TCG-Seattle and Qwest Corporation.)
- 01/29/1997 -- Approved (Approved per Consent Agenda.)