UTC Case Docket Details
Docket Number 240004
| Docket Number | UE-240004 |
|---|---|
| Advice | 2024-03 |
| Company | Puget Sound Energy |
| DBA | |
| Filing Type | Tariff Revision |
| Industry (Code) | Electric (140) |
| Status | Closed |
| Lead Staff | Hawkins-Jones, Jacque (UTC) |
| Filed Date | 01/03/2024 |
| Effective Date | 03/16/2024 |
| Summary | General Rate Case revising Tariff No. WN U-60 to increase base rate tariff schedules for recovery of revenue requirements. (Do Not Change Summary.) |
Event History
- 11/12/2026 -- Allowed (Commissioner Doumit moved in dockets UE-240004 and UG-240005 that the commission enter an order finding the Puget Sound Energy’s filing meets the requirements in Order 09 and 07 in dockets UE-240004 and UG-240005. The order should include the determination that Baker River Hydro Electric Seepage Reduction project, Beaver Creek Wind and Cherry Point Substation project costs are prudent. The company does not need to refund amounts collected on those projects, subject to the following conditions: a.) Any business case adjustments in the 2026 General Rate Case, in dockets UE-250005 and UG-250006, affecting this provisional capital review project, including the prudence determination of the Microsoft 365 enablement project, be subject to refund pending commission order. )
- 11/18/2026 -- Closed
- 11/12/2026 -- Open Meeting
- 03/29/2024 -- Consolidate - Parent
- 03/06/2024 -- Formal
- 03/05/2024 -- Consolidate - Child
- 01/03/2024 -- Pending
- 01/03/2024 -- Open