Filing TR - 170060
| Document Type |
Date |
Description |
| Memorandum |
07/02/2019 |
Closing memo to file.
|
| Agreement |
08/22/2018 |
Second Revised Project Agreement from Jeff Rivers for Snohomish County Public Works. (via email)
|
| Order - Other |
08/16/2018 |
Order Amending Commission Order 01 Authorizing Additional Expenditure from the Grade Crossing Protective Fund and Extension of Time to Complete Project.
|
| Letter |
08/15/2018 |
Request for additional disbursement of funds and extension of time to complete project from Snohomish County Public Works.
|
| Agreement |
01/05/2018 |
Signed revised project agreement from Snohomish County Public Works
|
| Order - Other |
11/27/2017 |
Order Granting Extension of Time to Complete Project and Submit Request for Reimbursement
|
| Email |
11/16/2017 |
Request for extension of time to complete project from Jeff Rivers for Snohomish County.
|
| Agreement |
03/20/2017 |
Signed project agreement on behalf of Snohomish County from Doug McCormick.
|
| Order - Other |
03/08/2017 |
Order Granting Petition to Install Highway-Rail Grade Crossing Active Warning Devices at 48th Avenue NW and Authorizing Expenditure from the Grade Crossing Protective Fund
|
| Initial Filing |
01/27/2017 |
Petition to Install Highway-Rail Grade Crossing Active Warning Devices at 48th Ave NW (USDOT #084683A) in Snohomish county and Disbursement of Funds from the Grade Crossing Protective Fund from the Snohomish County Public Works. (via email)
|