The commission issues a
complaint against Washington & Idaho Railway Inc. (WIR) alleging that WIR violated WAC
480-62-300 by failing to pay its annual report for the 2012 and 2013 reporting years, and alleging that WIR violated WAC 480-62-300 by failing to pay its regulatory fee for the 2012 and 2013 reporting year.
Pursuant to RCW 34.05.482 and WAC 480-07-610, the commission determines that a brief adjudicative proceeding is appropriate for determining whether the alleged violations occurred and, if so, the appropriate remedy for those violations.
The commission initially scheduled a
brief adjudicative proceeding in this matter for 9:30 a.m., on July 28, 2015, at commission headquarters in Olympia, Washington.
On July 23, 2015, commission staff notified the commission, by
letter, that the parties had reached a settlement in principle. The commission issued a
notice on July 23, suspending the procedural schedule in this matter. Parties must file either a settlement agreement and supporting documentation or a status report of their negotiations by August 21, 2015.
On September 9, 2015, the commission entered
Order 01 - Initial Order Approving Settlement Agreement. A copy of the Settlement Agreement can be viewed
here.
TR-143978 - All Documents