On December 29, 2014, Pacific Power & Light Company (Pacific Power) filed a
tariff revision with the commission updating its avoided cost tariff, Schedule 27. The commission suspended operation of the tariffs on February 12, 2015, by
Order 01 entered in this matter.
On April 2, 2015, the commission issued a
notice of prehearing conference setting this matter for a prehearing conference at 10:00 a.m., on April 23, 2015, at UTC headquarters in Olympia, Washington.
On April 23, 2015, the commission entered
Order 02, Prehearing Conference Order, setting a procedural schedule in this matter. The commission scheduled a hearing, allowing for oral argument on stipulated facts in this matter, for August 14, 2015, but by
notice issued on August 5, 2015, cancels the hearing.
UE-144160 - All documents