On August 31, 2017, Cascade Natural Gas Corporation filed with the commission revisions to its currently effective Tariff Wn U-3. Cascade is requesting authority to increase charges and rates for natural gas service by approximately $5.9 million, or 2.71 percent in base rates. On September 14, the commission entered Order 01, Complaint and Oder Suspending Tariff Revisions, initiating an adjudicative proceeding to determine if the proposed rates are fair and reasonable.
On September 18, 2017, the commission issued a notice, setting a prehearing conference which was held at 10 a.m., on October 9, 2017. On October 10, 2017, the commission entered Order 03, Prehearing Conference Order. Order 03, among other things, set the procedural schedule, including an evidentiary hearing to be held May 15-17, 2018 beginning at 9 a.m., in the commission's hearing room, second floor, Richard Hemstad Building, 1300 S. Evergreen Park Dr. SE, Olympia, Washington, 98504.
UG-170929 - All Documents